There is a flat rate fee per new component for design review services for public water systems.
Public Water System Design Review Application Types
|
Fee
|
Approval to Construct Public Water Supply Distribution System (Waterline):
Number of Service Connections: 150 or fewer (or 0 connections with 500+ ft of line)
151 to 300 301 to 450
451 to 600
601 to 750
Each additional 150
|
$1,284 $1,998
$2,711
$3,425
$4,138
Add $714
|
Water Treatment Plants and Blending Plans (including new source approval if applicable):
< 0.1 Million gallons per day (MGD)
≥ 0.1 MGD and < 1 MGD
≥ 1 MGD and < 5 MGD
≥ 5 MGD
|
$2,141
$2,854
$4,281
$7,135
|
Well (including new source approval if applicable)
|
$1,784
|
Storage Tank
|
$1,142
|
Booster Pump
|
$1,142
|
Main Line Extension (less than 500 ft of line)
|
$357
|
Chlorinators/Disinfection Devices
|
$357
|
Extension of Time to Construct
|
50% of the app fee, not to exceed $714
|
Priority Review Fee (Department authorization required)
|
Double the Standard Fee
|