Skip to main content

PUBLIC NOTICE | No Further Action Determination for the APS Prescott Manufactured Gas Plant Substation Voluntary Remediation Program (VRP) Site

Arizona Public Service Company (APS) has submitted a request for a No Further Action (NFA) determination to the Arizona Department of Environmental Quality (ADEQ) Voluntary Remediation Program (VRP) for the APS Prescott Manufactured Gas Plant (MGP) Substation VRP site.  The NFA requests closure for soil and was submitted in accordance with Arizona Revised Statutes § 49-181.

The APS Prescott MGP Substation VRP site consists of soils impacted by historic MGP operations located in Prescott, Arizona. Contaminants of concern at the site are a group of compounds commonly known as polynuclear aromatic hydrocarbons.

A determination of NFA means that no further action shall be taken by ADEQ to remediate or require remediation of the site or portion of the site covered by the no further action determination, except in limited circumstances described in statute | View A.R.S. 49-181(E) >

Review Documents & Site Page

Original Public Notice | View >
Remedial Action/No Further Action Report | View >

APS Prescott MGP Substation VRP Site Overview | View >

You may also review the above documentation at the ADEQ Record Center | Learn How >

Public Comment Period 

Dates: Feb. 23, 2021 – March 23, 2021

Comments may be submitted as follows:

     By Email to ADEQ | Send Email >
     By Mail to ADEQ (Must be postmarked or received by March 23, 2021):
       Attention: Nichole Osuch
       ADEQ Voluntary Remediation Program
       1110 W. Washington St.
       Phoenix, AZ 85007

or

     By Email to APS | Send Email >