All applications (Type 4 General Permit, Drinking Water Systems, and Subdivision) are subject to Licensing Time Frames (A.A.C. R18-1-525), which limits the number of business days ADEQ can review your project without a penalty. The Licensing Time Frames are summarized in the tables below.
Sewage Collection Systems and On-Site Wastewater (Septic) Treatment Facilities
| License Type |
Administrative Completeness Review |
Substantive Review |
Overall Time Frame |
| 4.01 300 Connections or less - (Combined pre and post construction) |
42 |
53 |
95 |
| 4.01 more the 300 Connections - (Combined pre and post construction) |
42 |
94 |
136 |
| Single 4.02, 4.03, 4.13, and 4.14 General Permits |
42 |
31 |
73 |
| 4.23 General Permit |
42 |
94 |
136 |
| Simple Combined Two or three Type 4 General Permits |
42 |
53 |
95 |
| Complex Combined Four or more Type 4 General Permits |
42 |
94 |
136 |
| Alternative design, installation, or operational feature to a Type 4 (Note 2) |
|
8 (Note 2) |
|
NOTES:
- Licensing Time Frames and licensing processes are defined in A.A.C. Title 18, Chapter 1, Article 5
. These are the number of days (business days excluding Sat, Sun, and all State holidays) that the agency has to process the application and come to a final decision. The counting of days may be stopped for requesting additional information from the applicant. The source of License Types and number of days is from R18-1 Article 5 published June 29th, 2007.
- Each request for an alternative design, installation, or operational feature under A.A.C. R18-9-A312(G) to a Type 4 General Permit adds eight business days to the substantive review time-frame.
Sanitary Facilities for Subdivisions
| License Type |
Administrative Completeness Review |
Substantive Review |
Overall Time Frame |
| Subdivision Community (Sewered) Facilities |
21 |
37 |
58 |
| Subdivision Individual (On-site) Facilities |
21 |
46 |
67 |
Drinking Water Treatment and Distribution Systems
| License Type |
Administrative Completeness Review |
Substantive Review |
Overall Time Frame |
| Standard drinking water treatment facility, project, or well approval to construct, |
16 |
37 |
53 |
| Complex drinking water treatment facility, project, or well approval to construct, |
16 |
67 |
83 |
| Standard drinking water treatment facility, project, or well approval of construction, |
16 |
37 |
53 |
| Complex drinking water treatment facility, project, or well approval of construction, |
16 |
67 |
83 |
| Standard drinking water new source approval, |
16 |
37 |
53 |
| Complex drinking water new source approval, |
16 |
67 |
83 |
| Drinking water time extension approval, |
16 |
16 |
32 |
Public and Semi-Public Swimming Pools and Spas
| License Type |
Administrative Completeness Review |
Substantive Review |
Overall Time Frame |
| Standard public and semi-public swimming pool design approval, |
26 |
26 |
52 |
| Complex public and semi-public swimming pool design approval, |
26 |
67 |
93 |
| Standard public and semi-public swimming pool approval of construction, |
26 |
26 |
52 |
| Complex public and semi-public swimming pool approval of construction, |
26 |
67 |
93 |
|