- The owner/operator of the facility submits the plan for ADEQ review. Three copies of the plan in the correct format must be submitted.
- An appropriate fee must be included with the application
- ADEQ notifies the appropriate city and county representatives
- ADEQ reviews the plan for administrative completeness and administrative completeness comments are addressed by the facility owner/operator.
- A public notice is issued following the administrative completeness review.
- ADEQ conducts the technical review and technical review comments are addressed by the facility owner/operator.
- Approval or denial of the application by ADEQ